Acceptance Testing a Robot Cell: The Plan to Write First

Published: Published on Zhilianhai

Two tests, two places

TestWherePurpose
Factory acceptance (FAT)At the integratorProve the cell works before shipping
Site acceptance (SAT)At your plantProve it works with your parts, people and power

Make the criteria numeric

“Works well” is not a criterion. Write the sample size, the acceptable cycle time range, the allowed intervention rate and the duration of the run. For example: 500 parts, cycle time within 5% of the agreed figure, no more than 2 manual interventions, safety functions verified against the risk assessment.

Test the failure paths

  • Stop and restart at every point in the cycle.
  • E-stop from each operator position, timed and recorded.
  • Power loss during a move, then recovery.
  • Bad part, missing part, upside-down part.
  • Network drop between robot and line controller.

Record each test with a date, the person who ran it and the result. That record is what the maintenance team will use for years.

Information is provided for initial research. Verify specifications, pricing, policies and standards against the original source before making decisions.

BackSection

Company information

Browse public company records in the company directory. To submit or correct company information, contact our team. Public inclusion does not imply supplier certification.

SectionLatestResources