Procurement Timeline for an Industrial Robot Project

Published: Published on Zhilianhai

Typical timeline

PhaseDurationNotes
Requirement and feasibility2-6 weeksTask study, concept, budget estimate
RFQ and vendor selection3-8 weeksInclude technical clarification rounds
Order to delivery6-20 weeksDepends on brand, options and workload
Integration and FAT4-12 weeksLonger for vision or complex tooling
Installation and SAT1-4 weeksPlant access dependent
Run-in to steady state4-12 weeksProductivity improves over time

The two dates that matter

Ask for the delivery date of the robot and the date the cell is expected to produce good parts. Vendors are usually confident about the first and vague about the second. Contract the second, with a definition of “good parts” attached.

Buffer for reality

Add contingency to the phases you control less: delivery of long-lead items and plant access during commissioning. A four-week slip is normal; a four-month slip usually means the requirement changed without being written down.

Information is provided for initial research. Verify specifications, pricing, policies and standards against the original source before making decisions.

BackSection

Company information

Browse public company records in the company directory. To submit or correct company information, contact our team. Public inclusion does not imply supplier certification.

SectionLatestResources