Payment Milestones for Robot Projects

Published: Published on Zhilianhai

A workable default

MilestoneShareTrigger
Order and design freeze20-30%Signed drawings and long-lead order placed
Build completion20-30%Machine assembled, ready for FAT
FAT passed20-30%Protocol signed, defects closed
SAT passed10-20%Accepted at the plant
Retention5-10%Released after 30-90 days of stable running

Why the retention line matters

Retention aligns the last invoices with the period when problems surface. It should be released automatically on the agreed date unless a documented defect is outstanding — a mechanism both sides can predict.

Tie every payment to evidence

Each milestone should name the document that proves it: the signed protocol, the photo, the test report. Payments triggered by “progress” are paid late and argued about; payments triggered by evidence are routine.

Information is provided for initial research. Verify specifications, pricing, policies and standards against the original source before making decisions.

BackSection

Company information

Browse public company records in the company directory. To submit or correct company information, contact our team. Public inclusion does not imply supplier certification.

SectionLatestResources