Acceptance Testing Checklist for a Robot Cell

Published: Published on Zhilianhai

Test before you sign

AreaWhat to test
FunctionEvery operating mode and recovery routine
Cycle timeMeasured over a sustained run, not a single cycle
QualityFirst pass yield at the agreed sample size
SafetyStops, interlocks and guards verified and recorded
DocumentsPrograms, parameters, spare list and training delivered
HandoverOperator and maintenance training completed

How to run the test

  • Agree the test plan and acceptance criteria in advance.
  • Record the run data and keep signed copies.
  • List any open defect with an owner and a date.

Acceptance criteria belong in the contract so that both sides test against the same measures.

Information is provided for initial research. Verify specifications, pricing, policies and standards against the original source before making decisions.

BackSection

Company information

Browse public company records in the company directory. To submit or correct company information, contact our team. Public inclusion does not imply supplier certification.

SectionLatestResources